Houghton – MTU – Dillman Window Replacement – Postponed

Non-mandatory walk-through date has been changed to Tuesday February 20, 2024 at 2 pm, per addendum #1. Meet in the lobby of Dillman Hall on the campus side of the building.

Project is postponed until the fall, due to issues related to removal of asbestos sealant, lead time for the windows, coordination of the demolition and install of the new windows.

Project Mgr: MTU Facilities Management

Architect: ZS Architectural Engineering

Website: View Site

Due Date: 02/29/2024 at 2:00 PM